Below are the major development axes identified for Dynaωo for the next few months, with associated contents and due date. It is important to notice that the development content and the due dates may be subject to change due to unforeseen complexity in implementing features or priority changes.
Axis 1 - Models development
PV and Wind WECC model: Available since V1.3.0HVDC standard model: expected September 2020: Available since V1.2.0Additional models for steady-state calculations (Static Var Compensator, voltage regulation, etc.): Available since V1.3.0- Standard regulation models (governors, voltage regulators, power system stabilizers): under progress
- IEC 61400 Wind model: under final validation, May 2022
Axis 2 - Test cases
- Adding large scale test cases (national and pan-European ones): internally ready but postponed to September 2022 (anonymisation) for public availability
New examples section: Available since V1.2.0.- NordicTestSystem case: under development, July 2022
ENTSO-E controller test caseAvailable since V1.3.0- Additional IEEE test cases: under validation, expected September 2022
Axis 3 - Dependencies, architecture and performances
Switch to Sundials V5.0.0 and Suitesparse V5.3.0: Available since V1.3.0Switch to a newer IIDM library version: Available since V1.3.0Performances improvements: Available since V1.2.2Ancilarry services - contingency analysis and margin calculation:Available since V1.3.0 for the new repository dynawo-algorithmsSwitch to MPI for multiple simulations (ancillary services): Available since V1.3.0- Critical clearing time algorithm: under validation, expected September 2022
- Symbolic Jacobian use for Modelica models: under development in OpenModelica, December 2022